Case Study:

Aggregate Plant - Massachusetts

TPS Installed a Plant Upgrade While the Existing Plant Was Operational

Our customer required a plant upgrade at one of their key locations. The plant provided more than one million tons of aggregate used in asphalt and other commercial products. The plant is located near a major urban city with high visibility. It was critical to the company that the existing plant stay operational as long as possible during the construction of the new secondary and tertiary plant. It was also critical to the customer that the plant be completed on time and within budget.

Project Details:

  • Location: Massachusetts
  • Project Size: $10 – $15 Million
  • Project Type:
    Aggregate Plant

Benefits Delivered:

  • Turn-Key Processing Solutions provided a fully automated, galvanized plant option for longer plant life and improved efficiency
  • TPS completed the installation of the plant while the existing plant was operational
  • The new secondary and tertiary plant was fully automated and upgraded, which improved the overall efficiency of the plant